Download Previous year Diploma Paper of Production Planning and Costing 6th Sem Dec 2016 Automobile Diploma Paper

Production Planning and Costing 6th Sem Dec 2016 Automobile Diploma Paper

                               SECTION-A

Q1. A) Fill in the blanks: 5×1=5
1. BIS stands for _____________
2. Process production is a ________ type of production
3. Catalogue price = _______________
4. Rent of building, depreciation cost comes under __________ overhead.
5. ______ is the process of predicting events, in advance.

B) Define the following: 5×2=10
1. Depreciation
2. Quality circle
3. Inspection
4. Follow up
5. Batch production

              SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30

a. Define PPC. What are its objectives?
b. Define the terms Routing, Loading and Scheduling?
c. What is Break Even Analysis? Write its assumptions
d. What is the role of operator within industry?
e. Write advantages and disadvantages of job production?
f. What are the different factors affecting Quality?
g. Write a note on Process sheet?

     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

i. What is dispatching? Write its functions and also discuss the different forms used during dispatching?
ii. What is ISO? What do you mean by ISO 9000? Write its characteristics and its aim?
iii. Differentiate b/w estimating and costing? Also define the different terms used in costing?
iv. Define production and productivity? What are the factors affecting productivity?

Production Planning and Costing 6th Sem dec 2016 Automobile Diploma Paper

Get Started

Section a Production Planning and Costing 6th Sem dec 2016 Automobile Diploma Paper

BIS stands for _____________

BIS stands for _____________

Process production is a ________ type of production

Process production is a ________ type of production

Catalogue price = _______________

Catalogue price = _______________

Rent of building, depreciation cost comes under __________ overhead.

Rent of building, depreciation cost comes under __________ overhead.

______ is the process of predicting events, in advance.

______ is the process of predicting events, in advance.

 

Define Depreciation

Depreciation

Define Quality circle

Quality circle

3. Inspection

 Inspection

Define Follow up

Follow up

Define Batch production

Batch production

Production Planning and Costing 6th Sem Dec 2016 Diploma Paper  Click Here

Section B :Production Planning and Costing 6th Sem dec 2016 Automobile Diploma Paper

Define PPC. What are its objectives?

PPC and its objectives.

Define the terms Routing, Loading and Scheduling?

Routing, Loading and Scheduling.

What is Break Even Analysis? Write its assumptions

Break Even Analysis and its assumptions

What is the role of operator within industry?

Role of operator within industry.

Write advantages and disadvantages of job production?

Advantages and disadvantages of job production.

What are the different factors affecting Quality?

Factors affecting Quality.

Write a note on Process sheet?

Process sheet.

Production Planning and Costing 6th Sem Dec 2016 Diploma Paper Click Here

Production Planning and Costing 6th Sem dec 2016 Automobile Diploma Paper

Get Started https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s

Section c :- Production Planning and Costing 6th Sem dec 2016 Automobile Diploma Paper

What is dispatching? Write its functions and also discuss the different forms used during dispatching?

Dispatching and its functions.

Discuss the different forms used during dispatching.

What is ISO? What do you mean by ISO 9000?

ISO and  ISO 9000.Write its characteristics and its aim.

Differentiate b/w estimating and costing?

Differentiate b/w estimating and costing.

Define production and productivity? What are the factors affecting productivity?

Production and productivity.

Factors affecting productivity.

vWrite short note on the following a. Concept of estimating

Concept of estimating

b. TQM

 TQM

c. Forecasting

Forecasting

Production Planning and Costing 6th Sem Dec 2016 Diploma Paper Contact Us
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering \"JK JK SMART CLASSES ER.JASWINDER KUMAR \"JK JK SMART LECTURE ER.JASWINDER KUMAR Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering \"JK ENGINEERING CLASSES ER.JASWINDER KUMAR \"JK er.jaswinder kumar Senior Lecturer