Download Previous Year Diploma Paper of Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Paper
Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Solved Question Paper
SECTION-A
Q1. a) Fill in the Blanks. 15×1=15
i. Number of bricks required for 1 Cu.m brick masonry is ____________
ii. Capitalized value = net annual rent × _________
iii. On acceptance of the tender % of the tendered amount has to be paid as security money.
iv. A reasonable profit usually % for contractor is included in the analysis of rates.
v. Total Dry material required for 1 cu.m cement concrete is ______ cu.m.
b) State the unit of measurement for the following.
vi. Earthwork
vii. Flooring
viii. Distempering
ix. D.P.C
x. Steel work
xi. Brick Work
xii. Electric Fitting
xiii. Welding
xiv. Skirting
xv. R.C.C. slab roofing
SECTION-B
Q2. Attempt any five questions. 5×6=30
a. What is valuation? Give the purpose of valuation.
b. What are the factors considered while preparing the analysis of rates?
c. Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
d. Find out the dry material required for 1 cu.m cement concrete 1:2:4.
e. Define tender. Write the name of various tender documents.
f. Define contractor. What are essential qualifications of a contractor?
g. Write a short note on Scrap value and Earnest money.
h. Write a short note on different Measurement Books.
i. Write a short note on Depreciation and Muster Roll.
SECTION-C
Q3. Attempt any three questions. 3×10=30
Q3. Prepare a preliminary estimate of a building having plinth area equal to 2000 sq.m. Given that:-
a. Plinth area rate – Rs. 2500/- per sq.
b. Extra for Architectural work – 1½% of the building cost.
c. Extra for Electrical Installation (10%), + Water supply and sanitary installations (6%) = 10+6=16% of the building cost.
d. Extra for other services- 8% of the building cost.
e. Contingencies and supervision charges 10%.
Q4. Workout the analyses of rates per cu.m for Brick work 1:4 cement sand mortar in superstructure.Labour for 10cu.m brick work is 8 brick layers @ Rs. 350/- per day, 15 mazdor @ Rs. 200/- , 2 Bhisti @ Rs. 250/- per day.
Rate of material:- cement bag Rs. 300/-, Sand Rs. 800/- per cu.m, Bricks = Rs. 3.5 per brick.
Q5. Define an estimate. Give its importance or objectives. Name the various types of estimate.
Q6. What is contract? Explain the different type of contract.
Q7. Work out the cost of earth work for a portion of a road from Rd 0 to Rd 90 meters from the following dates:
Rd | N.S. level | Formation Level |
0 | 205.00 | 210.00 |
30 | 205.60 | |
60 | 206.00 | |
90 | 206.80 | |
The formulation is in a downward gradient of 1 in 30. Formulation width is 10 meters and side slope 2:1(Horizontal: Vertical) Rate of earthwork is Rs. 400.00% cu.m
Q8. Work out the quantity of following items from the given drawing:-
Excavation for foundation
Cement concrete 1:6:18 in foundation
Mud Masonry in foundation and plinth
Mud Masonry in super structure
Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Question Paper
SECTION-A
Q1. a) Fill in the Blanks. 15×1=15
i. Number of bricks required for 1 Cu.m brick masonry is ____________
ii. Capitalized value = net annual rent × _________
iii. On acceptance of the tender % of the tendered amount has to be paid as security money.
iv. A reasonable profit usually % for contractor is included in the analysis of rates.
v. Total Dry material required for 1 cu.m cement concrete is ______ cu.m.
b) State the unit of measurement for the following.
vi. Earthwork
vii. Flooring
viii. Distempering
ix. D.P.C
x. Steel work
xi. Brick Work
xii. Electric Fitting
xiii. Welding
xiv. Skirting
xv. R.C.C. slab roofing
Get Started
Number of bricks required for 1 Cu.m brick masonry is ____________
Capitalized value = net annual rent × _________
On acceptance of the tender ______ % of the tendered amount has to be paid as security money.
A reasonable profit usually ______ % for contractor is included in the analysis of Rates.
Total Dry material required for 1 cu.m cement concrete is ______ cu.m.
State the unit of measurement for the following. vi. Earthwork
State the unit of measurement for the following vii. Flooring
State the unit of measurement for the following viii. Distempering
Give the unit of measurement for the following ix. D.P.C
Give the unit of measurement for the following x. Steel work
What are the unit of measurement for the following xi. Brick Work
What are the unit of measurement for the following xii. Electric Fitting
State unit of measurement for the following xiii. Welding
Give unit of measurement for the following xiv. Skirting
State unit of measurement for the following xv. R.C.C. slab roofingQuantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Paper Click Here
What is valuation? Give the purpose of valuation.Valuation and purpose of valuation.
What are the factors considered while preparing the analysis of rates?Factors considered while preparing the analysis of rates
Find out the dry material for 1 cu.m brick masonry in cement sand mortar 1:5.Dry material for 1 cu.m brick masonry in cement sand mortar 1:5.
Find out the dry material required for 1 cu.m cement concrete 1:2:4.Find out the dry material required for 1 cu.m cement concrete 1:2:4.
Define tender. Write the name of various tender documents.Tender and name of various tender documents.
Define contractor. What are essential qualifications of a contractor?Contractor and essential qualifications of a contractor
Write a short note on Scrap value and Earnest money.Short note on Scrap value and Earnest money.
Write a short note on different Measurement Books.Short note on different Measurement Books.
Write a short note on Depreciation and Muster Roll.Short note on Depreciation and Muster Roll.
Quantity Surveying & Valuation 6th Sem/Civil/May 2019 Diploma Solved Paper Click Here
Quantity Surveying & Valuation 6th Sem/Civil
/May 2019 Diploma Paper
Get Started
https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s
Prepare a preliminary estimate of a building having plinth area equal to 2000 sq.m.
Workout the analyses of rates per cu.m for Brick work 1:4 cement sand mortar in superstructure.
Define an estimate. Give its importance or objectives. Name the various types of estimate.Estimate and its importance or objectives
Name the various types of estimate.
What is contract? Explain the different type of contract.Contract and different type of contract.
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering

JK SMART CLASSES
ER.JASWINDER KUMAR

JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering

ENGINEERING CLASSES
ER.JASWINDER KUMAR

er.jaswinder kumar
Senior Lecturer