Download Previous Year Diploma Paper of Quantity Surveying & Valuation 6th Sem/Civil/Dec 2017 Diploma Paper
Quantity Surveying & Valuation 6th Sem/Civil/Dec 2017 Diploma Question Paper
SECTION-A
Q1. a) Fill in the Blanks. 15×1=15
a. Units of measurement of brick wall is __________________
b. No. Of brick in 1cum of brick masonry is _____________________
c. Bar bending schedule is made to find out quantity of ____________________
d. Dry material required for 1cum of cement concrete is________ cum
e. The livable area of a building at any floor is called ________________
b) State the unit of measurement for the following.
f. Dpc
g. Plastering
h. Concrete flooring
i. Painting
j. Erthwork
k. Cement concrete
l. Wood work in door frames
m. Railing
n. Brick work in foundation
o. Ashlar masonary
SECTION-B
Q2. Attempt any five questions. 5×6=30
a. What is rough cost estimate?
b. Write a short note on depreciation
c. Find out the dry material required for 10 cum cement concrete 1:2:4
d. Write a short note on sinking fund.
e. What is lump slump contract
f. What do you understand by specification of works
g. Write a short note on Role of contractor.
h. What do you know about Tender form?
SECTION-C
Q3. Attempt any three questions. 3×10=30
Q3 Find out material for Brick flooring 10 cm thick laid in cement mortar 1:5 over 10 cm thick cement concrete 1:6:18 over 10 cm sand filling.
Q4. What is contract, Explain different types of contract?
Q5. A part of road is to be constructed at a uniform rising gradient of 1 in 30. The NS levels are as follows
If the formation level at RD0 is 60m, Estimate the quantity of earth work for formation width of 10m. The site slope is 1:2 (Vertical: Horizontal) and there is no cross slope.
Q6. Workout the quantities of the following items from the given drawing :
(i) Earthwork in excavation.
(ii) First class brick work in cement mortar in foundation and plinth.
(iii) 2.5 cm cement concrete DPC
(iv) Fist class brick work in cement mortar 1:6 in super structure.
Get Started
Units of measurement of brick wall is __________________
No. Of brick in 1cum of brick masonry is _______________
Bar bending schedule is made to find out quantity of ____________________
Dry material required for 1cum of cement concrete is________ cum
The livable area of a building at any floor is called ________________
State the unit of measurement for f. Dpc
Give the unit of measurement for g. Plastering
What are the unit of measurement for h. Concrete flooring
State the unit of measurement for i. Painting
Give the unit of measurement for j. Erthwork
State the unit of measurement for k. Cement concrete
Give the unit of measurement for l. Wood work in door frames
What are the unit of measurement for m. Railing
State the unit of measurement for n. Brick work in foundation
Give the unit of measurement for o. Ashlar masonaryQuantity Surveying & Valuation 6th Sem/Civil/Dec 2017 Paper Click Here
What is rough cost estimate?Rough cost estimate
Write a short note on depreciationShort note on depreciation
Find out the dry material required for 10 cum cement concrete 1:2:4Calculate the dry material required for 10 cum cement concrete 1:2:4
Write a short note on sinking fund.Short note on sinking fund.
What is lump slump contract ?Lump slump contract
What do you understand by specification of works ?Specification of works
Write a short note on Role of contractor.Short note on Role of contractor.
What do you know about Tender form?Tender form
Quantity Surveying & Valuation 6th Sem/Civil/DEC 2017 Diploma Solved Paper Click Here
Quantity Surveying & Valuation 6th Sem/Civil
/DEC 2017 Diploma Paper
Get Started
https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s
Prepare a preliminary estimate of a building having plinth area equal to 2000 sq.m.
Workout the analyses of rates per cu.m for Brick work 1:4 cement sand mortar in superstructure.
Define an estimate. Give its importance or objectives. Name the various types of estimate.Estimate and its importance or objectives
Name the various types of estimate.
What is contract? Explain the different type of contract.Contract and different type of contract.
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering

JK SMART CLASSES
ER.JASWINDER KUMAR

JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering

ENGINEERING CLASSES
ER.JASWINDER KUMAR

er.jaswinder kumar
Senior Lecturer