77

Download Previous Year Question paper of QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

                                        SECTION-A

Q1. Attempt any Three questions.                                                                    5×3=15

a. Find out the dry material required for 100sq m cemetery plaster 1:4 (1.25 cm thick)
b. What is valuation? Give the purpose of valuation?
c. Define tender and earnest money?
d. Differentiate between security deposit and retention money?
e. What is rough estimate?
f. Write note on sinking fund?
g. Discuss the following terms
i) Scrap value ii) Market value iii) Rental return method of valuation

                                         SECTION-B

Q2. Attempt any one question.                                                       1×10=10

i. Prepare a preliminary estimate of a posh building with the following data
Plinth area rateRs 2500/sq m
Architectural design and drawing 1.5% of building cost
Water supply and sanitary Installation 10% of the cost of building
Electricity Installation Including fans etc. 14% of the cost of building
Extra for other service 6% overall Contingency 5% overall Supervision charges 3% overall
ii. What are the specifications of earth work in excavation of foundation?
iii. What is contractor system? What are types of contractor system? Explain each one in detail?
iv. Work out the quantities of following items from the given diagram
a) Excavation of foundation b) Cement Concrete 1:6:18 in foundation
c) Masonry in foundation and plinth d) Masonry in superstructure

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper


Get Started

Section A:-QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

Find out the dry material required for 100sq m cemetery plaster 1:4 (1.25 cm thick)

Dry material required for 100sq m cemetery plaster 1:4 (1.25 cm thick)

 What is valuation. Give the purpose of valuation?

Valuation and purpose of valuation.

Define tender and earnest money?

Tender and earnest money.

Differentiate between security deposit and retention money?

Differentiate between security deposit and retention money.

What is rough estimate?

Rough estimate.

Write note on sinking fund?

Sinking fund.

Discuss the following terms i) Scrap value ii) Market value iii) Rental return method of valuation

i) Scrap value

ii) Market value

iii) Rental return method of valuation

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper Click Here

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper


Get Started

https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s

Section B:-QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper

Prepare a preliminary estimate of a posh building with the following data Plinth area rateRs 2500/sq m Architectural design and drawing 1.5% of building cost Water supply and sanitary Installation 10% of the cost of building Electricity Installation Including fans etc. 14% of the cost of building Extra for other service 6% overall Contingency 5% overall Supervision charges 3% overall

Prepare a preliminary estimate of a posh building with the following data
Plinth area rateRs 2500/sq m
Architectural design and drawing 1.5% of building cost
Water supply and sanitary Installation 10% of the cost of building
Electricity Installation Including fans etc. 14% of the cost of building
Extra for other service 6% overall Contingency 5% overall Supervision charges 3% overall

 What are the specifications of earth work in excavation of foundation?

Specifications of earth work in excavation of foundation.

What is contractor system? What are types of contractor system? Explain each one in detail?

Contractor system and  types of contractor system. 

Work out the quantities of following items from the given diagram a) Excavation of foundation b) Cement Concrete 1:6:18 in foundation c) Masonry in foundation and plinth d) Masonry in superstructure

a) Excavation of foundation b) Cement Concrete 1:6:18 in foundation
c) Masonry in foundation and plinth d) Masonry in superstructure

QUANTITY SURVEYING AND VALUATION QSV 5th Sem/Civil/5156/Feb 2021 Diploma Paper Contact Us

Table of Contents

MY YOUTUBE CHANNEL

JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
\"JK
JK SMART CLASSES
ER.JASWINDER KUMAR
\"JK
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
\"JK
ENGINEERING CLASSES
ER.JASWINDER KUMAR
\"JK
er.jaswinder kumar
Senior Lecturer

Scroll to Top