Download Previous year Diploma Paper of Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper.
Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018
SECTION-A
Q1. Do as directed. 15×1=15
- Construction is the ultimate objective of a design.
- Bar Chart is also known as Gantt chart.
- Job diary is an important document for recording progress.
- DPC is laid to protect the building from moisture.
- Accidents are mishappening on construction projects.
- Payment of wages Act was passed in the year 1936.
- Military organization is the simplest and the earliest form of organization.
- Daily labor is paid on the basis of attendance marked on muster roll .
- First stage in Construction is conception .
- Financial year is always closed on 31st march every year.
b) State true or false.
- Design is a function of construction management. (False)
- Span control is not the principle of organization. (False)
- Control of quality delays the completion of project. (False)
- Line organization is flexible in nature. (False)
- Temporary advance can be recouped from time to time. (False)
SECTION-B
Q2. Attempt any five questions. 5×6=30
- What is relationship between owner and engineer in a construction team?
- Differentiate between PERT & CPM.
- What are the resources of Construction Industry?
- What is the difference between Imprest & Temporary advance.
- What are the causes of accidents on construction site?
- Define scheduling. Enlist its important advantages.
- Explain the following:(any two)
i) Activity ii)Event iii) Critical Path
8.Enlist the important stages of inspection in construction work?
SECTION-C
Q3. Attempt any three questions. 3×10=30
- Discuss the various stages in planning a construction project.
- Explain Line & staff organization. What are its advantages?
- What are the functions of construction management?
- Explain the term wages. What are different forms of wages?
- What is the difference between stock & tool and plant accounts?
Construction and Accounts CMA 6th Sem Civil Exam /5170/May 2019
Get Started
https://www.youtube.com/watch?v=y_wJffQkeWo&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=6&t=0shttps://www.youtube.com/watch?v=mV41CMWonN4&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=7&t=0shttps://www.youtube.com/watch?v=M_RR6LVICp0&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=20&t=0shttps://www.youtube.com/watch?v=3BNQLUnbNpYhttps://www.youtube.com/watch?v=ZDkyNOzoG8A&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=8&t=0shttps://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s
Section a FILL IN THE BLANKS Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper
_______ is the ultimate objective of a design.
Construction is the ultimate objective of a design.
Bar chart is also known as _______
Bar Chart is also known as Gantt chart.
Job diary is an important document for ________
Job diary is an important document for recording progress.
DPC is laid to protect the building from ________
DPC is laid to protect the building from moisture.
Accidents are __________ on construction projects.
Accidents are mishappening on construction projects.
Payment of wages Act was passed in the year ______.
Payment of wages Act was passed in the year 1936.
Military organization is the ________ and the earliest form of organization.
Military organization is the simplest and the earliest form of organization.
Daily labor is paid on the basis of attendance marked on __________.
Daily labor is paid on the basis of attendance marked on muster roll
First stage in Construction is ________.
First stage in Construction is conception
Financial year is always closed on __________.
Financial year is always closed on 31st march every year.
b) State true or false.
Design is a function of construction management.
(False)
Span control is not the principle of organization
(False)
Control of quality delays the completion of project.
(False)
Line organization is flexible in nature.
(False)
Temporary advance can be recouped from time to time.
(False)
Download Previous Year Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Click Here
Section B :Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper
What are the functions of owners in construction team?
Relationship between owner and engineer in a construction team
Differentiate between PERT & CPM.
Differentiate between PERT & CPM.
What are the resources of Construction Industry ?
Resources of Construction Industry
What is the difference between Imprest & Temporary advance ?
Difference between Imprest & Temporary advance.
What are the causes of accidents on construction site?
Causes of accidents on construction site
Define scheduling. Enlist its important advantages.
Scheduling its important advantages.
Explain the following:(any two) i) Activity ii)Event iii) Critical Path
Explain the following:(any two)
i) Activity ii)Event iii) Critical Path
Enlist the important stages of inspection in construction work ?
Important stages of inspection in construction work
Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper Click Here
Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018
Get Started
https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s
Section c :-Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019
Discuss the various stages in planning a construction project
Various stages in planning a construction project.
Explain Line & staff organization. What are its advantages?
Line & staff organization and its advantages
What are the functions of construction management ?
Functions of construction management
Explain the term wages. What are different forms of wages?
term wages. What are different forms of wages
What is the difference between stock & tool and plant accounts ?
Difference between stock & tool and plant accounts
Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Contact Us
MY YOUTUBE CHANNEL
JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
JK SMART CLASSES
ER.JASWINDER KUMAR
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
ENGINEERING CLASSES
ER.JASWINDER KUMAR
er.jaswinder kumar