Download Previous year Diploma Paper of Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper.

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018

                                        SECTION-A

Q1. Do as directed.                                                                                     15×1=15

  1. Construction is the ultimate objective of a design.
  2. Bar Chart is also known as Gantt chart.
  3. Job diary is an important document for recording progress.
  4. DPC is laid to protect the building from moisture.
  5. Accidents are mishappening  on construction projects.
  6. Payment of wages Act was passed in the year 1936.   
  7. Military organization is the simplest  and the earliest form of organization.
  8. Daily labor is paid on the basis of attendance marked on muster roll        .
  9. First stage in Construction is conception                .
  10. Financial year is always closed on 31st march every year.

b) State true or false.

  1. Design is a function of construction management.           (False)
  2. Span control is not the principle of organization.               (False)
  3. Control of quality delays the completion of project.          (False)
  4. Line organization is flexible in nature.                                  (False)
  5. Temporary advance can be recouped from time to time. (False)

              SECTION-B

Q2. Attempt any five questions.                                                                    5×6=30

  1. What is relationship between owner and engineer in a construction team?
  2. Differentiate between PERT & CPM.
  3. What are the resources of Construction Industry?
  4. What is the difference between Imprest & Temporary advance.
  5. What are the causes of accidents on construction site?
  6. Define scheduling. Enlist its important advantages.
  7. Explain the following:(any two)

           i) Activity         ii)Event        iii) Critical Path

        8.Enlist the important stages of inspection in construction work?

     SECTION-C

Q3. Attempt any three questions.                                                       3×10=30

  1. Discuss the various stages in planning a construction project.
  2. Explain Line & staff organization. What are its advantages?
  3. What are the functions of construction management?
  4. Explain the term wages. What are different forms of wages?
  5. What is the difference between stock & tool and plant accounts?

Construction and Accounts CMA 6th Sem Civil Exam /5170/May 2019


Get Started

https://www.youtube.com/watch?v=y_wJffQkeWo&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=6&t=0shttps://www.youtube.com/watch?v=mV41CMWonN4&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=7&t=0shttps://www.youtube.com/watch?v=M_RR6LVICp0&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=20&t=0shttps://www.youtube.com/watch?v=3BNQLUnbNpYhttps://www.youtube.com/watch?v=ZDkyNOzoG8A&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=8&t=0shttps://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s

Section a FILL IN THE BLANKS Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper

_______ is the ultimate objective of a design.

Construction is the ultimate objective of a design.

Bar chart is also known as _______

Bar Chart is also known as Gantt chart.

Job diary is an important document for ________

Job diary is an important document for recording progress.

DPC is laid to protect the building from ________

DPC is laid to protect the building from moisture.

Accidents are __________  on construction projects.

Accidents are mishappening  on construction projects.

Payment of wages Act was passed in the year ______.

Payment of wages Act was passed in the year 1936.   

Military organization is the ________  and the earliest form of organization.

Military organization is the simplest  and the earliest form of organization.

Daily labor is paid on the basis of attendance marked on __________.

Daily labor is paid on the basis of attendance marked on muster roll

First stage in Construction is ________.

First stage in Construction is conception                

Financial year is always closed on __________.

Financial year is always closed on 31st march every year.

State true or false.

b) State true or false.

Design is a function of construction management. 

(False)

Span control is not the principle of organization

(False)

Control of quality delays the completion of project. 

(False)

Line organization is flexible in nature.   

(False)

Temporary advance can be recouped from time to time.

(False)

Download Previous Year Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Click Here

Section B :Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper

What are the functions of owners in construction team?

Relationship between owner and engineer in a construction team

Differentiate between PERT & CPM.

Differentiate between PERT & CPM.

What are the resources of Construction Industry ?

Resources of Construction Industry

What is the difference between Imprest & Temporary advance ?

Difference between Imprest & Temporary advance.

What are the causes of accidents on construction site?

Causes of accidents on construction site

Define scheduling. Enlist its important advantages.

Scheduling its important advantages.

Explain the following:(any two)            i) Activity         ii)Event        iii) Critical Path

Explain the following:(any two)

           i) Activity         ii)Event        iii) Critical Path

Enlist the important stages of inspection in construction work ?

Important stages of inspection in construction work

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018 Paper Click Here

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2018


Get Started

https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0s

Section c :-Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019

Discuss the various stages in planning a construction project

Various stages in planning a construction project.

Explain Line & staff organization. What are its advantages?

Line & staff organization and its advantages

What are the functions of construction management ?

Functions of construction management 

Explain the term wages. What are different forms of wages?

term wages. What are different forms of wages

What is the difference between stock & tool and plant accounts ?

Difference between stock & tool and plant accounts

Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Contact Us
MY YOUTUBE CHANNEL

JK Smart Classes Upload Lecture for Degree classes like B.TECH,M.TECH in any stream like ECE,EE,ME and Civil Engineering
\"JK
JK SMART CLASSES
ER.JASWINDER KUMAR
\"JK
JK SMART LECTURE
ER.JASWINDER KUMAR
Engineering Classes Upload Lecture for Polytechnic Diploma classes in any stream like ECE,EE,ME and Civil Engineering
\"JK
ENGINEERING CLASSES
ER.JASWINDER KUMAR
\"JK
er.jaswinder kumar
Senior Lecturer

Scroll to Top