Download Previous year Diploma Paper of Construction and Accounts CMA 6th Sem Civil Exam/5170/Feb 2021 Paper.
Construction and Accounts CMA 6th Sem Civil Exam/5170/Feb 2021
 Duration: 1.15Hrs.                                 M.Marks:25    Session-MorningÂ
                     SECTION-A
Q1. Attempt any THREE questions.                                  3×5=15
i. What are the factors affecting the choice of particular gauge?
ii. Why coning of wheels is done in railways?
iii. What are the functions of fish plates?
iv. What are the advantages and disadvantages of timber sleepers?
v. Name the various tools required for track maintenance.
vi. Define and draw sketches of the following: A) Deck Bridge B) Through Bridge
vii. What are the advantages and disadvantages of tunnels?
viii. What do you understand by wing walls? Enumerate the types of wing walls.
                      SECTION-B
Q3. Attempt any ONE question.                            1×10=10
a. Explain different operations involved in the construction of tunnel.
b. What do you mean by failure of rails? Explain different types of failure of rails.
c. What is signalling? What are the objects of signalling? Explain absolute block system of signalling.
d. What are abutments? Explain different types of abutments in detail with sketches.
e. What are the various factors which effect the selection of bridge site?   Â
Construction and Accounts CMA 6th Sem Civil Exam/5170/Feb 2021
Get StartedSection a FILL IN THE BLANKS Water Supply & Waste Water Engg. 4th Sem Civil/0514/Dec 2015 Paper
Art of planning, co-coordinating and controlling various activities of a construction project is known as _______The art of planning, co-coordinating and controlling various activities of a construction project is known as Reduce.
Bar chart is also known as _______Bar chart is also known as Gantt chart.
Â
Line organization is not suitable for ______ projects.Line organization is not suitable for large projects.
_________ should be installed at the construction site to prevent fire hazards.Fire extinguishers should be installed at the construction site to prevent fire hazards.
The minimum wages Act was passed in the year 1948.
Â
A notebook which records the quantities of work done at the site periodically is termed as ________.A notebook which records the quantities of work done at the site periodically is termed as measurement book.
Quality control is achieved through routine _______.Quality control is achieved through routine inspection.
An event occurring unexpectedly during construction work is known as _______.An event occurring unexpectedly during construction work is known as accident.
A book which records cash transactions related to receipts and payments is _______.A book which records cash transactions related to receipts and payments is cash book.
Military organization is the ______ and the earliest form of organizationMilitary organization is the simplest and the earliest form of organization.
Â
b) State true or false.
The function of engineer is to arrange finances for the project.Â(False)
Â
CPM is activity based network.Â(True)Â Â Â Â Â Â Â Â Â Â
Â
Motivation of employees is not the need of organization.   (False)
The muster roll is used to mark the attendance of labour. Â(True)
Â
About 80 percent accidents are caused due to unsafe practices and shear negligence. Â(True)
Download Previous Year Construction and Accounts CMA 6th Sem Civil Exam/5170/FEB 2021 Click Here
Section A :Construction and Accounts CMA 6th Sem Civil Exam/5170/Feb 2021
What are the factors affecting the choice of particular gauge?Factors affecting the choice of particular gauge.
Coning of wheels is done in railways.
Functions of fish plates.
Advantages and disadvantages of timber sleepers.
Tools required for track maintenance.
Draw sketches of the following: A) Deck Bridge B) Through Bridge
Advantages and disadvantages of tunnels.
Wing walls and types of wing walls.
Define the following. (anytwo) Activity     b)Event       c)Dummy activity                 d) critical patha) Activity     b)Event       c)Dummy activity                 d) critical path
What are the limitations of bar charts ?Limitations of bar charts
Construction and Accounts CMA 6th Sem Civil Exam/5170/May 2019 Paper Click Here
Construction and Accounts CMA 6th Sem Civil Exam/5170/Feb 2021
Get Started https://www.youtube.com/watch?v=UHX6f8TIvX8https://www.youtube.com/watch?v=M_RR6LVICp0https://www.youtube.com/watch?v=mV41CMWonN4https://www.youtube.com/watch?v=s0LVPE0Q3LE&list=PLA9Q9SDZ781WXNAWit379A4CRLMvjGiUw&index=14&t=0sSection B :-Construction and Accounts CMA 6th Sem Civil Exam/5170/FEB 2021
Explain different operations involved in the construction of tunnel.Different operations involved in the construction of tunnel.
Failure of rails? Explain different types of failure of rails.
c. What is signalling? What are the objects of signalling? Explain absolute block system of signalling.
d. What are abutments? Explain different types of abutments in detail with sketches.
e. What are the various factors which effect the selection of bridge site?
Signalling and objects of signalling
Abutmentsand different types of abutments in detail with sketches.
Various factors which effect the selection of bridge site.